Reporting
Les rapports périodiques et finaux
Les rapports des projets représentent une obligation contractuelle.
Durant le projet, vous devez soumettre un rapport périodique dans les 60 jours après chaque "reporting period". Le rapport intermédiaire inclut:
| Scientific Work Progress report | |
|
0. Decalartion by the scientific representative of the project coordinator | by coordinator |
| 3. Work Progress, achievements during the period | by WP leaders (with partners contributions) + coordinator |
| 4. Deliverables and Milestones Tables | by coordinator |
| 4. WPs Deliverables and Milestones table for the period | by coordinator |
| 5. Project Management | by coordinator |
| 6. Explanation of the use of the ressources | by each partners |
| 7. FInancial statements - Forms C | by each partners via SESAM tool (inscription via ECAS) - Voir cartouche Force |
| 8. Certificates on financial statement (if applicable) | by each partners |
A la fin du projet, vous devrez soumettre, en plus du dernier rapport périodique, et dans les 60 jours:
| 1. Final Publishable Summary | by coordinator |
| 2. Use and Dissemination of foreground | by coordinator with WP leaders' help |
| 3. Report on social implication | by coordinator |
Rappel: Tenir "Timesheets" pour toutes les personnes travaillant sur le projet. Chaque partenaire/institution utilise son propre modèle selon ses règles internes et les instructions de la CE.